NWEC has been engaged to supply, fabricate, deliver and install Reefer Gantries, Signage and Substation structures for the Port Botany Terminal T3 Expansion project (Stages 1 & 2). In order to achieve revised timelines for the overall terminal the installation of the Reefer Gantries had to be done in just 4 x days per gantry. NWEC achieved this by re-engineering the design to allow for off-site modularised assembly and thus fast on-site installation.
Specific scope of work:
- Fabrication, delivery & installation of 4 x
- 24m high Reefer gantries & walkways
- Fabrication, delivery and installation of a
- Seaside and Landside Signage Gantries
- Fabrication, delivery and installation of
- Substation structure
Key issues to success:
- Re-engineering for modularisation
- Integration of equipment & electrics
- Safe lift planning and execution
- Shutdown planning & resourcing
- Flexibility to absorb late design changes
- Close integration with other works